The Operation

A swine and beef processing facility, with a capacity of 500-750 head per day, produced an effluent discharge of 30,000 gallons per day. It was using a 40 hp turbine for aeration at a cost for electricity of $2,000 per month. Chemical flocculants were also required to contol solid build-up, at a cost of $4,000 per month.


The Challenge

In 1997, a $700,000 wastewater remediation system from Europe was installed. Solids build-up continued to the point that the pond was 95% crusted over and there were very strong odors with numerous community complaints.


Click on thumbnail to view full-size image

THE O2 SOLUTION® System was installed in June of 2001, and the results speak for themselves:

PROJECT #1 PRIMARY WASTEWATER POND

 
BOD
TSS
DO
Date:
(MG/L)
(MG/L)
(MG/L)
05/09/01
286
3120
<0.1

AGSMART SYSTEM INSTALLED JUNE, 2001

 
BOD
TSS
DO
09/04/02
82
1950
2.68
Percentage
71%
38%
268%
Change
Reduction
Reduction
Increase



Click on thumbnail to view full-size image.

Odor complaints ceased to be an issue, and a community open house brought many compliments.


 

 